Tongaat Hulett insurance appeal, Digimart Global (South Africa): Tongaat Hulett has lost its appeal to pursue a R52.4 million insurance claim by its Mozambican subsidiary against two Mozambican insurers in South Africa. The Supreme Court of Appeal handed down its judgment on 20 November, ruling that the dispute lacked a sufficient connection to the country.
The claim arose from damage to equipment at Tongaat Hulett’s Xinavane sugar mill in Maputo Province, Mozambique, in 2009. The companies claimed R52 377 947 under a Contract Works Policy and a Project Delay Insurance Policy, which covered physical damage to construction works and business interruption arising from an insured event.
The majority found that the policies were concluded in Mozambique, the insured risk materialised there and the alleged breach occurred there. The court also rejected arguments that the South African and Mozambican companies formed an insured joint venture, and that the Mozambican insurers were merely alter egos of their South African counterparts.
The ruling does not dismiss all claims against the Mozambican insurers. According to the report, the majority found the insurers had submitted to the Durban High Court’s jurisdiction over claims by the two South African plaintiffs, who claimed the same amount as consequential loss, provided they can establish them.
The original proceedings were instituted in the KwaZulu-Natal High Court in Durban in September 2011.
Judge of Appeal David Unterhalter disagreed with the majority in a separate judgment, arguing the claims were sufficiently interconnected to be heard together and that requiring Xinavane to litigate in Mozambique would be costly and wasteful. The majority’s decision prevailed, and the appeal was dismissed with costs.
The judgment comes as Tongaat Hulett remains in business rescue, which began in October 2022. According to the report, the Industrial Development Corporation injected a further R200 million earlier this year, bringing its post-commencement funding commitment to R2.5 billion. The post-commencement facility remains available until 30 November, the same day as its final repayment date.