NextDC Pledges No New Datacentres Near Homes After Melbourne Community Backlash

NextDC datacentre community backlash Melbourne: Datacentre operator NextDC says it will no longer pursue new developments near homes after community backlash to an expansion of its M3 site in West Footscray, in inner Melbourne, according to a report published by The Guardian. The backlash led to a delay of the controversial expansion after power provider Jemena paused construction of new.

NextDC datacentre community backlash Melbourne, Digimart Global (West Footscray, Melbourne): Datacentre operator NextDC says it will no longer pursue new developments near homes after community backlash to an expansion of its M3 site in West Footscray, in inner Melbourne, according to a report published by The Guardian. The backlash led to a delay of the controversial expansion after power provider Jemena paused construction of new 22-metre power poles amid community protest, and NextDC’s share price dropped 40%.

The share price has since recovered to over $9 a share, but not before rival Goodman Group bought a nearly 10% stake in the business. At the company’s first annual general meeting since the delay, shareholders issued a second strike against executive pay, but a motion on whether to spill the board was defeated.

Chief executive Craig Scroggie said it was his “hardest AGM” in 15 years and that he took responsibility for “delivery, power, planning, approvals, construction and community support”. He said the company needed to work more closely with its power and construction partners and with the community, and that residents should have been heard earlier during the Jemena construction works.

In response, NextDC says it will set up a new community consultative committee, including a standing forum for residents and local stakeholders, along with a dedicated project website and contact channels with defined response times for complaints and inquiries. Scroggie said community expectations about datacentres have shifted in the age of artificial intelligence and that the company must move with them.

NextDC chair Doug Flynn said the company does not intend to pursue new development opportunities near residential properties given community sensitivities. He said the pushback against datacentres is very different now than it was about six years ago, and noted that the M3 site had been an industrial site for 100 years and had petrochemical works on it before NextDC built the datacentre.

Flynn also said the Jemena employee overseeing community engagement had left the business after the backlash to taller power poles. A Jemena spokesperson declined to comment but pointed to a September statement announcing that its general manager for electricity networks had decided to step down.

Callum Fletcher

Callum Fletcher covers international news, Australian sports, entertainment, and cultural developments. His reporting focuses on major global events and trending stories relevant to audiences throughout Australia.
Copy Profile

Leave a Reply

Your email address will not be published. Required fields are marked *

Sports

Explore Digimart Global