City Power switching station, Digimart Global (Johannesburg, South Africa): City Power says its R180m switching station at Pennyville is intended to reduce the risk of electricity outages disrupting water supply in Johannesburg. The project is 68% complete and is expected to be finished in April, according to the utility.
The station is designed to allow electricity to be redirected when substations experience faults or are taken offline for maintenance. City Power says this is aimed at protecting critical water infrastructure operated by Rand Water and Johannesburg Water, following earlier reporting by TimesLIVE on the link between electricity failures and water shortages in Johannesburg dating back to July.
How the new station will work
City Power spokesperson Isaac Mangena said the new switching station would strengthen connections between substations, including Fordsburg, Orlando, Eikenhof, Mondeor and Prospect. He said the upgrades would give City Power more options to restore electricity when parts of the network were affected.
The new station will have remote switching technology linked to City Power’s Control Centre. This will allow operators to transfer electricity between routes, isolate faults and redirect supply where capacity allows.
Part of wider network upgrades
The Pennyville project forms part of City Power’s wider network upgrades, including work at Mondeor substation. According to Mangena, the connection between Mondeor and Eikenhof is between 90% and 95% complete, which he said would help keep critical infrastructure running during electricity interruptions.
Mangena said the project began in 2016 to address the ageing Orlando Switching Station and improve connections between the eastern and western parts of the electricity network. Electrical equipment is now being installed at the Pennyville site, and overhead transmission lines that crossed the station have been removed to make way for the new infrastructure.
Planned maintenance at Delta substation
In line with the project, Mangena said City Power will conduct planned maintenance at Delta substation on Tuesday. He said the work will involve transferring and reconnecting cables between stations as part of the wider network upgrades.