Limpopo road project, Digimart Global (Mopani District, Limpopo): A long-stalled road upgrade in Limpopo is now close to opening to traffic, according to The Citizen. The 33km, R400 million project stretches from D15 Morebeng to D3232 into the Sekgosese communities under Greater Letaba Local Municipality, and was abandoned by contractors a few years after it was commissioned in 2017.
The project was widely criticised over allegations of corruption, inefficiency and political interference, with claims that it was used as a pawn by politicians seeking votes between election seasons. The road was meant to connect eight villages across Mopani and Capricorn districts, linking the Morebeng and Sekgosese/Tshabelane communities.
President Cyril Ramaphosa visited the stalled gravel-to-tar route in February 2022, after local government elections and two years before the 2024 provincial and national elections. According to the report, several ANC leaders and officials had allegedly promised him the project was nearing completion and would open before the 2024 polls.
The project then missed a series of completion deadlines.
In response, Premier Phophi Ramathuba ordered that the road be completed and instructed a forensic investigation by the provincial Department of Public Works, Roads and Infrastructure. The probe covers allegations that a senior manager at Roads Agency Limpopo (RAL) irregularly paid the failed contractor.
RAL has confirmed that the manager paid the contractor a R20 million retention fee before the project was closed out.
A new contractor, Mathothoka Trading CC, was appointed on 18 August 2025 to complete the remaining work at a cost of R107 483 304. The company had originally promised to finish before the end of 2025. RAL CEO Makhitha Chesane told The Citizen that 3.5km of road had been tarred, and that the road and bridges were expected to be ready between December and January.
The Department of Public Works spokesperson, Tendani Munyai, said the scope includes 3.5km of Road D3150 and two bridges. Structural work on Bridge 1 is complete and backfilling is under way.
Bridge 2 required additional span length after severe flooding between December 2025 and March 2026, and construction is targeted for completion on 30 January 2027.
Residents interviewed by The Citizen said the road would significantly cut travel times, with one saying the trip from Wholesale to Soekmekaar, which took about two hours, would take around 30 minutes. Others were more cautious and said the project should be judged once it is fully finished.
The contractor’s managing director, George Dukwara, said he was optimistic about completing the project on time and noted that it created 37 local jobs.