Durban Port Backlog Likely to Last Into January, Transnet Says

Durban port backlog: Transnet says congestion at Durban Gateway Terminal will likely persist into January, delaying critical medicine shipments and festive season stock for retailers. Operator ICTSI is bringing in new equipment, with full functionality expected to take up to three years, while businesses and industry groups report mounting losses from delays.

Durban port backlog, Digimart Global (Durban, South Africa): Congestion at Transnet’s Durban Gateway Terminal (DGT) is likely to persist into January, further delaying critical medicines for conditions such as high cholesterol, high blood pressure and stomach ulcers. Transnet group COO Solly Letsoalo told Business Day on Monday that the backlog is expected to ease but not clear by December.

Letsoalo said the terminal could take up to three more years to become fully functional, as its Philippines-based operator, International Container Terminal Services (ICTSI), brings in new equipment and carries out essential refurbishment. ICTSI began managing the terminal in January under a 25-year concession, in which it holds a 49% stake while Transnet retains 51% ownership.

Business and health impacts

Several business groups say the port problems are hurting their members. The Citrus Growers’ Association of Southern Africa said logistics backlogs had resulted in missed market supply windows, contributing to a worse-than-anticipated 2026 export season.

On Tuesday, retailer Pepkor warned that operational problems at South African ports and delayed stock deliveries could undermine trade in the coming months, including festive season sales.

Last week, parliament heard that health minister Aaron Motsoaledi had appealed to transport minister Barbara Creecy to help expedite the release of medicine shipments held up at the terminal, which have contributed to unprecedented drug shortages in the public health sector. Transnet said that of 41 containers identified by the health department as requiring urgent processing, 18 had been cleared and delivered, while seven were expected to arrive in South Africa by next Wednesday.

Causes and the operator’s record

The terminal has been grappling with a pile-up of vessels since August, when a new operating system glitched. That failure coincided with peak citrus export season, and Letsoalo said the backlog had never been recovered.

Pepkor said the problems at the Port of Durban were partly linked to serious delays at ports of origin, particularly in China, as well as shipping difficulties in Pakistan and India, but were also systemic and included challenges involving the new operator, labour and equipment.

Letsoalo said the terminal was sitting on a backlog of roughly 10 or 11 vessels a day that could not berth as soon as they arrived. He said ICTSI’s 11-month record at the terminal should be judged in light of its limited equipment, and that the operator would handle more containers once it received new equipment.

Longer-term outlook

Transnet said that during 2025, while still under Transnet Port Terminals, DGT recorded sustained operational recovery, with average ship turnaround time improving from about 105 hours in April to about 97 hours in December. Letsoalo said that to shorten the timeline, the upgrade will be done in stages, with phase one completed in about a year and a half using new equipment.

The Southern African Association of Freight Forwarders and Business Unity SA said the DGT difficulties show that private sector participation is a mechanism rather than an outcome in itself, and that reform must be judged by additional freight moved, improved reliability, shorter turnaround times and lower end-to-end logistics costs.