Sudbury road construction season: Orange cones are slowly disappearing from roads in Greater Sudbury as winter arrives and summer projects near completion. According to the city's senior project manager, Andrew Peltomaki, crews are preparing for the season. Peltomaki said asphalt plants are scheduled to close in the coming weeks, so the main focus is getting roads paved and ready for.

Sudbury road construction season, Digimart Global (Greater Sudbury, Ontario): Orange cones are slowly disappearing from roads in Greater Sudbury as winter arrives and summer projects near completion. According to the city’s senior project manager, Andrew Peltomaki, crews are preparing for the season.

Peltomaki said asphalt plants are scheduled to close in the coming weeks, so the main focus is getting roads paved and ready for winter. Some concrete work remains, including curbs and sidewalks that need to be tidied up before snow falls.

He said there are maybe 10 to 15 jobs ongoing.

Speed bumps added on seven roads

David Knutson, the city’s manager of traffic and transportation, said speed bumps were installed on seven roads during the construction season to address speeding concerns in the community. The goal is to increase compliance with posted speed limits and lower speeds on city streets.

Knutson said the city is in close communication with its winter operations staff, and that existing speed bumps elsewhere in the community have caused no issues for winter snow removal.

Events centre progress

The largest project in the city is the new events centre under construction in the Brady Street area. Antti Velkko, general manager of community infrastructure, said about 70 per cent of the project’s underground mechanical pipes are complete.

Velkko said a large amount of concrete is being poured and formed for pile caps and great beams, with foundations roughly 20 per cent complete. Concrete for the floor is expected to be poured starting in December, with structural steel installation targeted to begin in January.

The arena remains on track for its 2028 completion date.