32,016 Social Housing Units Blocked or Delayed Across South Africa, SHRA Tells Parliament

social housing projects South Africa: Social housing projects South Africa: The Social Housing Regulatory Authority told Parliament that 65 projects affecting 32,016 units are blocked or delayed, citing cost escalation, insolvency, weak oversight and funds released before projects were secure. It aims to resolve 17 projects by December 2028.

Social housing projects South Africa, Digimart Global (South Africa): The Social Housing Regulatory Authority (SHRA) has revealed that 65 housing projects affecting 32,016 social housing units across South Africa are blocked or delayed. The authority presented the findings to Parliament on Wednesday, according to the publisher report.

The SHRA identified governance failures, rising construction costs, insolvency and weak oversight as factors undermining the programme. Biansha Van Staden, the authority’s Acting Chief Executive Officer, said projects failed because of cost escalation, delivery agent governance failures, insolvency, business rescue, weak historical oversight, grant funding released before projects were secure, and weak contract administration.

The SHRA acknowledged that public funding had in some instances been released before projects were secure. The scale of the challenge includes four distressed projects and eight delayed or incomplete projects, and the authority also reported five active litigation matters.

The SHRA and the Department of Human Settlements presented a recovery strategy to the Portfolio Committee on Human Settlements. The strategy aims to resolve 17 blocked and delayed projects affecting 9,378 units and approximately 17,400 housing opportunities by December 2028. By December 31, 2028, the authority says every project currently classified as blocked should reach an end-state, meaning completed and occupied, transferred to a capable institution, curtailed through an approved process, or legally concluded.

Van Staden said the authority intends to recover public funds where project obligations were not met and to hold professionals accountable. Success will be measured by units unblocked, units completed and tenanted, projects reaching end-state, funds recovered, and improvements in occupancy and rent collection.

Dr. Alec Moemi, Director-General of the Department of Human Settlements, said the department had studied the presentation and accepted the proposals.

He said the department and SHRA would prioritise finishing stalled projects before approving new ones. Moemi added that the department continues investigations and referrals to the Special Investigating Unit where wrongdoing has occurred.