Essex intersection partial reopening, Digimart Global (Essex, Ontario): A major Essex road project will not fully reopen as planned because a supplier has delayed traffic signal equipment. Mayor Sherry Bondy says reconstruction of the Maidstone Avenue and Talbot Street North intersection is substantially complete, but the town is still waiting on traffic signal poles and arms.
To ease congestion and improve access to nearby businesses, the town and contractor are aiming for a partial reopening before November 27. Under the plan, Talbot Street would reopen to traffic while Maidstone Avenue remains closed as crews finish the remaining work.
Bondy said the project itself has stayed on schedule, noting that favourable weather allowed contractors to anticipate opening the intersection as originally planned. The delay now involves infrastructure for poles and streetlights.
The intersection has been under construction since August as part of a $3-million reconstruction project. Bondy said businesses near the work zone are still feeling the impact, and some reported sales drops of as much as 40 per cent earlier this year.
She said the partial reopening should provide some relief, particularly for businesses on the other side of Talbot Street, which have asked for more communication about timing.
The town, Essex Centre BIA and economic development staff have promoted a “Worth the Drive” campaign encouraging residents to keep shopping in the area despite detours. Bondy said the finished project should improve traffic flow and help prepare the town for future growth.
The town says an official notice with reopening dates, a revised completion timeline and any impacts on the Essex Christmas Parade is expected later this week.