Eskom Workers at Hendrina and Arnot Uncertain About Jobs as Coal Station Closures Near

Eskom workers uncertainty: Eskom workers: employees at Hendrina and Arnot power stations in Mpumalanga say they are uncertain about their futures as planned closures by 2030 approach, while formal reskilling programmes have yet to begin, according to a parliamentary oversight visit and a Cape Times report.

Eskom workers uncertainty, Digimart Global (Mpumalanga, South Africa): Eskom employees at the Hendrina and Arnot coal-fired power stations in Mpumalanga have raised concerns about their future employment, as formal reskilling and upskilling programmes have yet to get under way. Both stations are scheduled for closure by 2030.

The concerns emerged during parliamentary oversight visits by the Portfolio Committee on Electricity and Energy over the weekend, which assessed Eskom’s preparations for the transition. According to a Parliament statement, station management told committee members that uncertainty about the future was contributing to anxiety among employees.

The Cape Times reported on the workers’ concerns.

Management said formal reskilling could only begin once the skills requirements for the planned new technologies had been established, meaning uncertainty was likely to persist until workers had a clearer picture of what would happen when the stations closed. Committee members questioned why formal programmes had not started, given that about four years remained before the planned shutdowns.

Committee chairperson Zamakhanyase Khanyase said job security concerns were widespread among employees at power stations identified for decommissioning. The committee said it intended to raise the issues with Eskom and the Presidential Climate Commission, and stressed that the decommissioning process must be guided by a Just Energy Transition, with practical programmes to protect and empower affected workers and communities.

Lessons from Komati

The concerns follow the committee’s visit to the Komati Power Station on Friday. Komati ceased commercial electricity generation in October 2022 and is being converted into a renewable energy facility.

Members of Parliament questioned whether the station had been shut down without a sufficiently detailed and coordinated plan to address socio-economic consequences, and organised labour called on Eskom not to close other earmarked coal stations until the Komati repowering project was fully operational.

According to the committee, Eskom management acknowledged shortcomings, conceding that Komati had not provided an ideal example of a just energy transition, and said it was incorporating lessons from the project into future planning. The committee also noted reports that the closure of Komati and an adjoining coal mine had affected community services, including a clinic, emergency ambulance services and sporting facilities.