Patriotic Alliance donations Joburg contracts, Digimart Global (Johannesburg, South Africa): IOL reports that Metrowired, an ICT company based in Woodmead, gave the Patriotic Alliance (PA) R380,000 between October and December 2023. The company has since won more than R16.5m in work from the Metropolitan Trading Company (MTC), a City of Johannesburg entity.
The MTC runs the city’s broadband network and was placed under the transport portfolio by a council resolution in June 2023, four months after Kenny Kunene was appointed the city’s transport political head. Kunene is now the PA deputy president.
The MTC advertised panels for ICT and smart city solutions in the 2024/25 financial year, and its ICT panel tender, which closed on January 15 2025, called for service providers to complement its capacity for 36 months.
The report draws a parallel to Downtown Spares, a company owned by Mario Francis, which also paid the PA R380,000 between October and December 2023. According to the IEC’s party funding disclosure report, Downtown Spares paid two amounts of R190,000 on October 27 and November 10 2023. The IEC said those payments went towards the party’s gala dinner in November 2023 and ordinarily should not have been declared as donations, but that it published them as the party declared them.
Downtown Spares won a Joshco contract worth R48,968,713.20 between July and September 2023, the quarter before those payments. The contract was to convert a building at 57 Mentz Street in Booysens into 40 social housing flats.
At the time, the PA’s Anthea Leitch was the city’s mayoral committee member for human settlements, the portfolio that oversees Joshco. Joshco said the procurement followed its supply chain management policy and that Downtown Spares took part through a contractor rotation system.
Progress on the Booysens project has been slow. Joshco handed over the site on January 21 2025, about 18 months after the award, and its completion date has been moved twice, from October 22 2025 to May 8 2026, and then to December 10 this year.
By June 30 this year Joshco had spent R27.86m and put physical progress at 45%. Its performance report attributed the delays to retail tenants who refused to vacate and took Joshco to court, to late payments by Joshco, and to the contractor’s slow progress and lack of money.
IOL said Kunene and a representative of Metrowired were asked for comment and that their responses would be added once received. The report has not been independently verified, and the article does not establish that the donations influenced the awards.